PLM Phase 1 Project Plan

1 Introduction

1.1 Purpose of this document

This document is inteded to serve as the project plan for the first phase of the PLM implementation.

2 Project Life Cycle

2.1 Life Cycle Method

We will be using a SCRUM like method. More to follow here. http://devel.opensaf.org/~scon/diagram01.png

2.2 Phase Delverables

2.2.1 Requirements and Design Phase (aka "pre-game" phase )

DocumentDescriptionOwnerDelivery DateStatus
SRS (Software Requirements Specification)Defines the software requirements for the projectJonas ArndtReview Draft Avaiable nowIn Review
High Level DesignIncludes Architectural descriptionAnil Sadineni1st draft Aug 18thIn progress
Use CasesThis document will provide details on the use cases that will be part of the Phase 1 implementation. Jonas ArndtReview Draft expected Aug 21st In progress
Domain Model and class diagramDescription of the objects and how they interact with each otherAnil SadineniReview draft Aug 10th Available for review
Detailed Design specificationThis document will serve as the Internal reference Specification (IRS). It will document all internal interfaces needed to implement the Use Cases identified for the first implementation of PLM. We will assume the PLM specification will act as the External Reference Specification (ERS)Jonas Arndt???In Progress.